ICCP Deep Anode Bed — KAUST Sheet Piles Protection

Project Controls Dashboard · Cost, Schedule & Progress
BEA MEA MACC KAUSTKAUST
Overall health — AMBER
Site Progress Photos
Project LeadEng. Mohamad Deeb
Budget (BAC)SAR 466,000
P.O. Number83842
Date updated1 November 2026
ReportWeekly Progress Report #02
Baseline programme19 Jul – 11 Jan 2027
Activities59
SourceExport - Anode Bed MACC Project 01-Nov-26 .xlsx
01

Executive summary

Reporting date 1 November 2026 · weekly progress report #02 · P.O. 83842

Weighted physical progress
35.47%earned
+0.31 ptsagainst 35.17% planned at the data dateahead of plan
Performance indices
1.01
SPI
0.99
CPI
SV +SAR 1,425 · CV −SAR 1,700
Forecast completion
11 Jan 2027
baseline 11 Jan 2027 · on date
AugOctDec1 Nov 2611 Jan 27106 of 177 days elapsed71 days left19 Jul
Cost position
35.8%spent
SAR 165,300earned value
of SAR 466,000 budget
PVSAR 163,875
EVSAR 165,300
ACSAR 167,000
Earned value (EV)
SAR 165,300
35.47% of the budget at completion
Planned value (PV)
SAR 163,875
35.17% of the budget at completion
Actual cost (AC)
SAR 167,000
35.84% of the budget at completion
Budget at completion
SAR 466,000
P.O. Number 83842
Estimate at completion
SAR 470,792
VAC −SAR 4,792 on recorded cost · provisional
Activities
59
8 completed · 2 in progress · 49 not started
Key dates in the schedule
8
2 achieved · 2 in progress · 4 ahead
Critical activities
1
zero total float, of 59 · 5 within two days

Overall health — AMBER

Schedule performance is rated GREEN at this data date and the other four dimensions AMBER, measured against the baseline dates, the weightage and the cost columns of the export of 1 November 2026.

RatingDimensionBasis
GREENSchedule performanceSPI 1.01 at the data date: earned value SAR 165,300 against planned value SAR 163,875, schedule variance +SAR 1,425; weighted progress 35.47% against 35.17% planned, +0.31 pts. All 59 activities sit on their baseline dates; the position is earned progress, not a date slip.
AMBERCompletion dateThe forecast lands on 11 Jan 2027, the baseline date, but 68% of the weighted value is unearned with 106 of 177 days gone, and the driving chain (9.1 → 9.2 → the three drillings → 12 → 14) carries 0 to 1 day of float. The date holds only while the drilling sequence holds.
AMBERCost performanceCPI 0.99 and CV −SAR 1,700 on SAR 167,000 of cost recorded; EAC SAR 470,792 against the budget of SAR 466,000 (VAC −SAR 4,792). The material package is fully costed (SAR 126,000) while the installation lines carry no cost yet and 9.1 shows SAR 1,000 of a SAR 10,000 line: the index describes procurement, not the works.
AMBERCritical pathOnly 1 of the 59 activities has zero total float (14, the final dossier) and 5 sit within two days, but the chain that carries the finish runs through all three anode beds: 11.1.3, 11.2.3 and 11.3.3 are three 8-day drillings at SAR 35,000 each, one after the other, and 11.3.3 ends eight days before the last energisation test.
AMBERData qualityThree items need closing: 9.1 reports 10% against a window that opens on 7 November and carries no actual start or finish; 10.2 reports 90% with a finish of 2 November, the day after the data date; and the summary rows repeat their children's cost, so the Baseline Cost column totals SAR 1,157,000 against the SAR 466,000 budget although the weightage itself sums to 100% over the leaf activities.
02

Progress against the plan

Cumulative weighted progress and the planned value per month

PlannedEarned

S-curve — cumulative weighted progress

Planned 35.17% · earned 35.47% · +0.31 pts at the data date

0%025%116,50050%233,00075%349,500100%466,000AugSepOctNovDecJanearned 35.47%planned 35.17%SAR

Planned curve from the baseline dates and the activity weightage. The export carries one data date only (report #02), so the earned position is the single point of 1 November 2026 and no earlier earned curve exists to draw.

Planned value per month

Baseline distribution · total SAR 466,000

Jul51kAug71kSep24kOct91kNov184kDec29kJan1 Nov
July 2026SAR 15,7993.4%
August 2026SAR 51,01210.9%
September 2026SAR 70,75515.2%
October 2026SAR 24,1845.2%
November 2026SAR 91,18119.6%
December 2026SAR 183,56939.4%
January 2027SAR 29,5006.3%
03

Workstreams

Actual against planned by WBS package

Progress by workstream

Planned marker · actual bar

Engineering & Documentation
7 · 4.7% weight · 4 activities
100.00%0.00 pts
Delivery of Material
8 · 27.0% weight · 3 activities
100.00%0.00 pts
Site Preparation & Permits
9 · 5.8% weight · 2 activities
3.70%+3.70 pts
Underground Utilities Scanning
10 · 3.9% weight · 2 activities
90.56%+2.36 pts
Installation of Anode Bed
11 · 53.4% weight · 45 activities
0.00%0.00 pts
Energization & Commissioning
12 · 3.2% weight · 1 activity
0.00%0.00 pts
Site Demobilization & Clearing
13 · 0.6% weight · 1 activity
0.00%0.00 pts
Final Dossier & As-built
14 · 1.3% weight · 1 activity
0.00%0.00 pts

Where the weight sits

Share of the SAR 466,000 budget

8packages
  • Engineering & Documentation4.7%
  • Delivery of Material27.0%
  • Site Preparation & Permits5.8%
  • Underground Utilities Scanning3.9%
  • Installation of Anode Bed53.4%
  • Energization & Commissioning3.2%
  • Site Demobilization & Clearing0.6%
  • Final Dossier & As-built1.3%
04

Schedule timeline

The eight dated packages, baseline bars, progress and the data date

AugSepOctNovDecJanEngineering & documentation100.00% of 4.72%Material delivery100.00% of 27.04%Site preparation & permits3.70% of 5.79%Underground utilities scanning90.56% of 3.86%Installation of anode bed0.00% of 53.43%Energization & commissioning0.00% of 3.22%Demobilization & clearing0.00% of 0.64%Final dossier & as-built0.00% of 1.29%data date

Bars are the baseline dates of each package. Solid teal is the part already earned; the dashed outline is the remaining window. The red line is the data date, 1 November 2026.

05

Cost and earned value

Planned, earned and actual by package

PV · EV · AC by workstream

SAR at the data date

PVEVAC
0k63k126k7891011121314SAR

Earned value metrics

At the data date

Cost variance (EV − AC)−SAR 1,700
Schedule variance (EV − PV)+SAR 1,425
Cost performance index0.990
Schedule performance index1.009
Estimate at completionSAR 470,792
Variance at completion−SAR 4,792
Budget spent to date35.84%
Cost still to spendSAR 299,000
Value still to earnSAR 317,000

Cost and progress by workstream

SAR at the data date

WBSWorkstreamWeightPVEVACCVCPI
7Engineering & Documentation4.72%SAR 22,000SAR 22,000SAR 22,000SAR 01.00
8Delivery of Material27.04%SAR 126,000SAR 126,000SAR 126,000SAR 01.00
9Site Preparation & Permits5.79%SAR 0SAR 1,000SAR 1,000SAR 01.00
10Underground Utilities Scanning3.86%SAR 15,875SAR 16,300SAR 18,000−SAR 1,7000.91
11Installation of Anode Bed53.43%SAR 0SAR 0SAR 0SAR 0n/a
12Energization & Commissioning3.22%SAR 0SAR 0SAR 0SAR 0n/a
13Site Demobilization & Clearing0.64%SAR 0SAR 0SAR 0SAR 0n/a
14Final Dossier & As-built1.29%SAR 0SAR 0SAR 0SAR 0n/a
–Total100.00%SAR 163,875SAR 165,300SAR 167,000−SAR 1,7000.99

Where a workstream has no cost posted (the whole of 11, 12, 13 and 14) its CPI is not yet meaningful.

06

Status and float

Activities by status, and the tightest floats in the logic

Activities by status

59 activities in the export

59activities
  • Completed8
  • In progress2
  • Not started49

The two open activities are 9.1 mobilisation (10%) and 10.2 scanning (90%).

Total float — tightest twelve open activities

Calendar days, from the logic links of the export

14 Project Final Docier - Asbuilt DRG, Reports..
0 d
11.3.12 Termination, Labeling..
1 d
11.3.13 Assessment, Modification & Integration of Rect.Trans
1 d
11.3.14 Pre-Commissioning Test
1 d
12 Energization & System Commissioning & HO
1 d
11.3.11 Installation of Andoe Junction Box
8 d
11.3.8 System Test
9 d
11.3.9 Backfilling
9 d
11.3.10 Installing of Concrete Foundation
9 d
11.3.6 Borhole Field Test
10 d
11.3.7 Installation of Anode Bed System
10 d
11.2.6 Borhole Field Test
11 d

Red is zero float, orange two days or less, amber five days or less. Only 14 carries zero; the rest of the driving chain carries 0 to 1 day.

07

Key dates

The eight dated package closes, with the forecast at the data date

WBSPackageBaseline finishForecast finishVarianceStatusProgress
7Engineering & Documentation23 Aug 202623 Aug 2026on dateComplete100.00%
8Delivery of Material12 Oct 202612 Oct 2026on dateComplete100.00%
9Site Preparation & Permits14 Nov 202614 Nov 2026on dateIn progress3.70%
10Underground Utilities Scanning02 Nov 202602 Nov 2026on dateIn progress90.56%
11Installation of Anode Bed05 Jan 202705 Jan 2027on dateNot started0.00%
12Energization & Commissioning07 Jan 202707 Jan 2027on dateNot started0.00%
13Site Demobilization & Clearing31 Dec 202631 Dec 2026on dateNot started0.00%
14Final Dossier & As-built11 Jan 202711 Jan 2027on dateNot started0.00%

The export carries no contractual milestone list: these are the completion dates of the eight dated packages (WBS 7 to 14) as printed.

08

Decisions and checkpoints

What needs deciding this week, and where the plan stood at each control date

Key decisions required

Five decisions from the export of 1 November 2026

  • 1
    Confirm mobilisation before 7 November (9.1)
    9.1 Mobilization carries SAR 10,000 and reports 10% against a window that opens on 7 November, with no actual start or finish in the export: the figure is ahead of its own dates. It is also the first activity of the driving chain. Decision: confirm on site whether mobilisation really started and record the actual date, because 9.1 → 9.2 → 11.1.1 decide the 15 November start of the installation.
  • 2
    Close the underground scanning and link the clearance (10.2)
    10.2 GPR & EML/RD Survey reports 90% with a finish of 2 November, the day after the data date, and no successor in the export, so the clearance it produces is not linked to any drilling. Decision: sign off the survey report this week and link 10 to 11.1.3, otherwise the 23 November drilling of bed L2 starts on an untracked clearance.
  • 3
    Fix the rig sequence across the three beds (11.1.3 / 11.2.3 / 11.3.3)
    The three drillings at SAR 35,000 each — SAR 105,000, 22.5% of the budget — run one after another on the same chain: L2 23 Nov – 1 Dec, L1 3 – 12 Dec, L6 14 – 22 Dec, each in an 8-day window. Decision: confirm the rig and crew can hold those three windows back to back; 11.3.3 is what ends the driving chain before energisation.
  • 4
    Post cost as the installation starts (AC vs EV)
    Actual cost SAR 167,000 against earned value SAR 165,300 (CPI 0.99): the material package is fully costed at SAR 126,000 while the installation lines carry nothing and 9.1 shows SAR 1,000 of its SAR 10,000. SAR 299,000 of spend is still to come. Decision: agree with finance how the subcontract, rig and disposal costs of 11 are coded and posted month by month, so CPI and EAC describe the works and not the lag in cost capture.
  • 5
    Protect the installation window, 15 November – 5 January
    68% of the weighted value of the works is still unearned and it sits almost entirely in 11 (53.43%), between 15 November and 5 January. Only 1 activity has zero float and 5 are within two days, so there is no slack in the chain to absorb a late rig, a late material delivery or a permit. Decision: freeze the access, lifting and permit commitments for the three beds now.

Planned vs actual — checkpoints

Cumulative weighted progress at each control date

CheckpointWhat it measuresPlannedActualVariance
23 Aug 2026Engineering & documentation complete (7)
drawings, submittal, risk assessment and procurement closed
10.29%10.29%0.00 pts
12 Oct 2026Delivery of material complete (8)
ICCP material, civil accessories and inspection
31.76%31.76%0.00 pts
01 Nov 2026Data date — position reported now
report #02 of 1 November 2026
35.17%35.47%+0.31 pts

The two closing dates (23 August and 12 October 2026) closed exactly on plan; at the data date the position is 35.47% against 35.17% planned.

09

Reporting history

Newest first · the export carries one update

DateReportProgressPosition
01 Nov 2026Current Weekly progress report #02
data date 1 November 2026
35.47%
planned 35.17%
35.47% against 35.17% planned · +0.31 pts. Eight activities complete (engineering and material delivery), two in progress (9.1 mobilisation and 10.2 scanning). 68% of the value of the works — the three anode beds and the commissioning — is still ahead.

Report #01 is not part of this export, so the dashboard shows one data date and restates nothing.

10

Progress register

59 activities · dates, progress, weight, cost and float as printed in the export

Activities

Grouped by WBS package

WBSActivityStatusStartFinishDaysActual start% comp.WeightCostFloatVar. pts
7 · Engineering & Documentation4.7% weight · 19 Jul → 23 Aug
7.1Desgin DrawingsCompleted2026-07-192026-07-29102026-07-19100.0%3.22%SAR 15,000—+0.0
7.2Material SubmittalCompleted2026-07-222026-08-19252026-07-22100.0%0.21%SAR 1,000—+0.0
7.3Project Rist Assessments & MOSCompleted2026-07-312026-08-1092026-07-31100.0%1.07%SAR 5,000—+0.0
7.4Procurement & LogisticsCompleted2026-08-202026-08-2332026-08-20100.0%0.21%SAR 1,000—+0.0
8 · Delivery of Material27.0% weight · 13 Aug → 12 Oct
8.1ICCP MaterialCompleted2026-08-132026-10-04452026-08-13100.0%21.46%SAR 100,000—+0.0
8.2Civil & Installation AccessoriesCompleted2026-08-132026-10-04452026-08-13100.0%5.36%SAR 25,000—+0.0
8.3Material InspectionCompleted2026-10-052026-10-1272026-10-05100.0%0.21%SAR 1,000—+0.0
9 · Site Preparation & Permits5.8% weight · 07 Nov → 14 Nov
9.1Mobilization (Site, Equipment, Manpower...)In Progress2026-11-072026-11-147—10.0%2.15%SAR 10,00059+10.0
9.2Site Barricading, Clearing & Safety SetupPlanned2026-11-072026-11-147—0.0%3.65%SAR 17,00016+0.0
10 · Underground Utilities Scanning3.9% weight · 18 Oct → 02 Nov
10.1PTW & WICF Underground Utilities ScanningCompleted2026-10-182026-10-2572026-10-18100.0%0.21%SAR 1,000—+0.0
10.2GPR & EML/RD SurveyIn Progress2026-10-262026-11-0272026-10-2690.0%3.65%SAR 17,00071+2.5
11 · Installation of Anode Bed53.4% weight · 15 Nov → 05 Jan
11.1.1PTW & WICF - Dredging and ExcavtionPlanned2026-11-152026-11-227—0.0%0.21%SAR 1,00015+0.0
11.1.2Excavation & Trenching CP DuctPlanned2026-11-232026-11-264—0.0%1.72%SAR 8,00016+0.0
11.1.3Drilling of Anode BedPlanned2026-11-232026-12-018—0.0%7.51%SAR 35,00014+0.0
11.1.4CP Duct Installation, Testing, Concrete & BackfillingPlanned2026-11-282026-11-303—0.0%1.61%SAR 7,50042+0.0
11.1.5Dewatering & Water Quality ManagementPlanned2026-11-232026-12-018—0.0%1.07%SAR 5,00042+0.0
11.1.6Borhole Field TestPlanned2026-12-022026-12-021—0.0%0.64%SAR 3,00013+0.0
11.1.7Installation of Anode Bed SystemPlanned2026-12-022026-12-032—0.0%1.07%SAR 5,00032+0.0
11.1.8System TestPlanned2026-12-052026-12-051—0.0%0.54%SAR 2,50031+0.0
11.1.9BackfillingPlanned2026-12-062026-12-072—0.0%0.64%SAR 3,00031+0.0
11.1.10Installing of Concrete FoundationPlanned2026-12-082026-12-103—0.0%0.86%SAR 4,00031+0.0
11.1.11Installation of Andoe Junction BoxPlanned2026-12-122026-12-121—0.0%0.32%SAR 1,50030+0.0
11.1.12Termination, Labeling..Planned2026-12-122026-12-121—0.0%0.21%SAR 1,00027+0.0
11.1.13Assessment, Modification & Integration of Rect.TransPlanned2026-12-132026-12-142—0.0%0.21%SAR 1,00027+0.0
11.1.14Pre-Commissioning TestPlanned2026-12-152026-12-151—0.0%0.64%SAR 3,00027+0.0
11.1.15Site Restoration Horticulture & Land ScapingPlanned2026-12-082026-12-092—0.0%0.43%SAR 2,00033+0.0
11.2.1PTW & WICF - Dredging and ExcavtionPlanned2026-11-282026-12-057—0.0%0.21%SAR 1,00015+0.0
11.2.2Excavation & Trenching CP DuctPlanned2026-12-062026-12-094—0.0%1.72%SAR 8,00014+0.0
11.2.3Drilling of Anode BedPlanned2026-12-032026-12-128—0.0%7.51%SAR 35,00013+0.0
11.2.4CP Duct Installation, Testing, Concrete & BackfillingPlanned2026-11-282026-11-303—0.0%1.61%SAR 7,50037+0.0
11.2.5Dewatering & Water Quality ManagementPlanned2026-12-032026-12-128—0.0%1.07%SAR 5,00032+0.0
11.2.6Borhole Field TestPlanned2026-12-132026-12-131—0.0%0.64%SAR 3,00011+0.0
11.2.7Installation of Anode Bed SystemPlanned2026-12-142026-12-152—0.0%1.07%SAR 5,00020+0.0
11.2.8System TestPlanned2026-12-162026-12-161—0.0%0.64%SAR 3,00020+0.0
11.2.9BackfillingPlanned2026-12-172026-12-192—0.0%0.86%SAR 4,00020+0.0
11.2.10Installing of Concrete FoundationPlanned2026-12-202026-12-223—0.0%0.86%SAR 4,00019+0.0
11.2.11Installation of Andoe Junction BoxPlanned2026-12-232026-12-231—0.0%0.32%SAR 1,50019+0.0
11.2.12Termination, Labeling..Planned2026-12-232026-12-231—0.0%0.21%SAR 1,00017+0.0
11.2.13Assessment, Modification & Integration of Rect.TransPlanned2026-12-242026-12-241—0.0%0.21%SAR 1,00017+0.0
11.2.14Pre-Commissioning TestPlanned2026-12-262026-12-261—0.0%0.64%SAR 3,00016+0.0
11.2.15Site Restoration Horticulture & Land ScapingPlanned2026-12-012026-12-065—0.0%0.43%SAR 2,00037+0.0
11.3.1PTW & WICF - Dredging and ExcavtionPlanned2026-12-102026-12-177—0.0%0.21%SAR 1,00014+0.0
11.3.2Excavation & Trenching CP DuctPlanned2026-12-192026-12-224—0.0%1.72%SAR 8,00012+0.0
11.3.3Drilling of Anode BedPlanned2026-12-142026-12-228—0.0%7.51%SAR 35,00011+0.0
11.3.4CP Duct Installation, Testing, Concrete & BackfillingPlanned2026-12-232026-12-263—0.0%1.61%SAR 7,50012+0.0
11.3.5Dewatering & Water Quality ManagementPlanned2026-12-142026-12-228—0.0%1.07%SAR 5,00021+0.0
11.3.6Borhole Field TestPlanned2026-12-232026-12-231—0.0%0.64%SAR 3,00010+0.0
11.3.7Installation of Anode Bed SystemPlanned2026-12-242026-12-262—0.0%1.07%SAR 5,00010+0.0
11.3.8System TestPlanned2026-12-272026-12-271—0.0%0.54%SAR 2,5009+0.0
11.3.9BackfillingPlanned2026-12-282026-12-292—0.0%0.64%SAR 3,0009+0.0
11.3.10Installing of Concrete FoundationPlanned2026-12-302027-01-023—0.0%0.86%SAR 4,0009+0.0
11.3.11Installation of Andoe Junction BoxPlanned2027-01-032027-01-031—0.0%0.32%SAR 1,5008+0.0
11.3.12Termination, Labeling..Planned2027-01-032027-01-031—0.0%0.21%SAR 1,0001+0.0
11.3.13Assessment, Modification & Integration of Rect.TransPlanned2027-01-042027-01-041—0.0%0.21%SAR 1,0001+0.0
11.3.14Pre-Commissioning TestPlanned2027-01-052027-01-051—0.0%0.64%SAR 3,0001+0.0
11.3.15Site Restoration Horticulture & Land ScapingPlanned2026-12-272026-12-293—0.0%0.43%SAR 2,00011+0.0
12 · Energization & Commissioning3.2% weight · 06 Jan → 07 Jan
12Energization & System Commissioning & HOPlanned2027-01-062027-01-072—0.0%3.22%SAR 15,0001+0.0
13 · Site Demobilization & Clearing0.6% weight · 30 Dec → 31 Dec
13Site Demobilization & ClearingupPlanned2026-12-302026-12-312—0.0%0.64%SAR 3,00011+0.0
14 · Final Dossier & As-built1.3% weight · 09 Jan → 11 Jan
14Project Final Docier - Asbuilt DRG, Reports..Planned2027-01-092027-01-113—0.0%1.29%SAR 6,0000+0.0

Dates and figures are those of the export, unaltered. Weight is the share of the SAR 466,000 budget on each leaf activity; float is calculated from the printed logic; the last column is actual progress minus planned progress to the data date, in points of the activity.

11

Look-ahead

Open activities in the next one and two weeks · the bar places each window on the coming fortnight

1-week look-ahead

01 Nov → 08 Nov3 activities9.4% of the weightSAR 44,000 of value
WBSActivityWindow · to 15 NovStartFinishDaysStatusWeightCost
10.2GPR & EML/RD Survey
26 Oct02 Nov7In Progress3.65%SAR 17,000
9.1Mobilization (Site, Equipment, Manpower...)
07 Nov14 Nov7In Progress2.15%SAR 10,000
9.2Site Barricading, Clearing & Safety Setup
07 Nov14 Nov7Planned3.65%SAR 17,000

2-week look-ahead

01 Nov → 15 Nov4 activities9.7% of the weightSAR 45,000 of value
WBSActivityWindow · to 15 NovStartFinishDaysStatusWeightCost
10.2GPR & EML/RD Survey
26 Oct02 Nov7In Progress3.65%SAR 17,000
9.1Mobilization (Site, Equipment, Manpower...)
07 Nov14 Nov7In Progress2.15%SAR 10,000
9.2Site Barricading, Clearing & Safety Setup
07 Nov14 Nov7Planned3.65%SAR 17,000
11.1.1PTW & WICF - Dredging and Excavtion
15 Nov22 Nov7Planned0.21%SAR 1,000
12

Baseline and limits

Baseline against actual dates, and what the export does not carry

Baseline register

Baseline dates against the current dates of the export

ItemBaselineCurrent / actualVariance
Baseline start19 Jul19 Julon date
Baseline finish11 Jan 202711 Jan 2027on date
Programme duration177 days177 days—
7.1 Design drawings — finish29 Jul 202627 Jul 2026−2 d
8.1 ICCP material — finish04 Oct 202607 Oct 2026+3 d
8.2 Civil & installation accessories — finish04 Oct 202607 Oct 2026+3 d

All 59 activities carry the same start and finish in the baseline and current columns, so the schedule has not been re-baselined. The three lines above are the only differences recorded between baseline and actual dates.

Constraints

Shown as not in the schedule rather than filled in

  • Contractual milestones
    The eight dates in section 07 are package completions from the schedule, not contract milestones: the export carries no milestone list.
  • Resources
    The Resource and Notes columns are printed but empty on all 59 activities, so no crew, rig or subcontractor is named against the drillings.
  • Lag reasons
    Links carry FS/SS with lag 0 only; no reason is recorded for the relationships between the three beds.
  • Delay events, weather and access
    Not part of this export: no delay log, weather record or permit register is attached.
  • Progress history
    One data date (report #02). Report #01 is not in the file, so no weekly gain or trend is shown.
  • Cash flow by cost centre
    The export carries one actual cost per activity to date and no invoice or commitment register, so the forecast-to-complete by cost centre is not shown.
13

Notes on the data

How each figure is produced, and where the export is silent

14

Site progress photos

30 photographs of 1 November 2026, grouped by area · included in the printed report

Open the gallery
L6

CMOR L6 area

11 photographs
Total Station - Setup — L6
Total Station - SetupL6 · 1 Nov 2026
GPR - Utilities Survey — L6
GPR - Utilities SurveyL6 · 1 Nov 2026
Dredge Point Coordinates — L6
Dredge Point CoordinatesL6 · 1 Nov 2026
Utilities Scanning — L6
Utilities ScanningL6 · 1 Nov 2026
Verifing Undergriund Utilities — L6
Verifing Undergriund UtilitiesL6 · 1 Nov 2026
Verifing Undergriund Utilities — L6
Verifing Undergriund UtilitiesL6 · 1 Nov 2026
Verifing Undergriund Utilities — L6
Verifing Undergriund UtilitiesL6 · 1 Nov 2026
Verifing Undergriund Utilities — L6
Verifing Undergriund UtilitiesL6 · 1 Nov 2026
Verifing Undergriund Utilities — L6
Verifing Undergriund UtilitiesL6 · 1 Nov 2026
RD/EML Survey — L6
RD/EML SurveyL6 · 1 Nov 2026
Site photo — no caption in the export — L6
Site photo — no caption in the exportL6 · 1 Nov 2026
L2

ARAMCO L2 area

8 photographs
Verifing Underground Utilities — L2
Verifing Underground UtilitiesL2 · 1 Nov 2026
Verifing Underground Utilities — L2
Verifing Underground UtilitiesL2 · 1 Nov 2026
Verifing Underground Utilities — L2
Verifing Underground UtilitiesL2 · 1 Nov 2026
GPR Utilities Survey — L2
GPR Utilities SurveyL2 · 1 Nov 2026
Setting Dredging Coordinates — L2
Setting Dredging CoordinatesL2 · 1 Nov 2026
GPR Utilities Survey — L2
GPR Utilities SurveyL2 · 1 Nov 2026
Setting Dredg Point — L2
Setting Dredg PointL2 · 1 Nov 2026
Utilities Scanning — L2
Utilities ScanningL2 · 1 Nov 2026
DOW L1

DOW L1 area

11 photographs
GPR Utilities Survey — DOW L1
GPR Utilities SurveyDOW L1 · 1 Nov 2026
GPR Utilities Survey — DOW L1
GPR Utilities SurveyDOW L1 · 1 Nov 2026
GPR Utilities Survey — DOW L1
GPR Utilities SurveyDOW L1 · 1 Nov 2026
GPR Utilities Survey — DOW L1
GPR Utilities SurveyDOW L1 · 1 Nov 2026
Verifing Underground Utilities — DOW L1
Verifing Underground UtilitiesDOW L1 · 1 Nov 2026
RD/EML Utilities Scan — DOW L1
RD/EML Utilities ScanDOW L1 · 1 Nov 2026
GPR Utilities Survey — DOW L1
GPR Utilities SurveyDOW L1 · 1 Nov 2026
GPR Utilities Survey — DOW L1
GPR Utilities SurveyDOW L1 · 1 Nov 2026
Setting Dredging Coordinates — DOW L1
Setting Dredging CoordinatesDOW L1 · 1 Nov 2026
GPR Utilities Survey — DOW L1
GPR Utilities SurveyDOW L1 · 1 Nov 2026
GPR Utilities Survey — DOW L1
GPR Utilities SurveyDOW L1 · 1 Nov 2026

Captions are those printed in the “Site Progress Photos” sheet of the export, in its own order. The areas follow the print blocks of that sheet: the first two blocks are captioned CMOR L6 and ARAMCO L2, and the last two carry no area name in the file, so they are shown as DOW L1.

Weighted progress, earned value, SPI, CPI, EAC and float are calculated from the activity weightage, the reported percentage, the baseline dates, the cost columns and the logic links of Export - Anode Bed MACC Project 01-Nov-26 .xlsx. Nothing on this page is illustrative. · Project Lead Eng. Mohamad Deeb · P.O. 83842 · Data date 1 November 2026
ICCP Deep Anode Bed — KAUST Sheet Piles Protection
Prepared from the weekly export